REAL PLANT · BLINDMuse chose the same core revamp as Shell's engineers↗

For process engineers checking a plant change before MOC approval

Change the plant.Prove the change.

PlantAgent turns a P&ID and an engineering goal into a checked draft change. Meta's Muse models propose and revise; process and electrical engines decide what passes, what fails and what still needs an engineer.

Muse aloneProcess reaches 120 % ✓
PlantAgentApproval blocked: the transformer would be overloaded ✕

Open source · simulator-checked · every output stays a draft until an engineer approves it

INPUTP&ID + data sheets
PROPOSALMeta Muse
CHECKSEngineering engines
OUTPUTRev B + decision pack

Muse proposes. Physics checks. Engineers approve.

01 · PROPOSE

Muse works on the drawing

It reads the P&ID and source documents, builds a model, proposes a change and explains what it assumed.

02 · CHECK

Engines return the numbers

DWSIM, pandapower, WaterTAP and discipline checks re-solve the change. The model cannot mark its own work as passed.

03 · DECIDE

The engineer owns the outcome

Failures and open items stay visible. Approval freezes a revision with its evidence, comments and audit trail.

Built on Meta

One model stack, distinct jobs

Reading, designing and challenging are separate steps. Each simulation result comes back from an engine, not from the language model.

MetaMeta Muse
Muse WonderRead the plant

Scanned P&IDs, patent figures and data sheets.

Muse Spark OpenDesign the change

Open weights propose, read failures and revise.

Muse Spark 1.3Attack the design

Operating deviations test a passing design.

Muse VoiceCapture the goal

The engineer's spoken request enters the record.

Why open weights matter: the Meta-hosted endpoint refused the UCTE blackout prompt four times (content policy). Muse Spark Open ran the same engineering loop; redispatch plus opening the 220 kV tie passed line limits and N-1 (0 violations). An availability result, not a quality comparison.

UNSEEN DRAWINGBASF column K 2750

Open-weight Muse built the model and reached a 600 mm process-screened replacement.

Vendor confirmation open
REAL PLANT · BLINDShell Norco C2 splitter

Muse chose the same core revamp as Shell; it missed the published feed-tray move.

5 match · 3 partial · 1 miss
CROSS-DISCIPLINE BLOCKVacuum-salt plant

The process reaches +20%. The electrical model blocks approval at the transformer.

Process passes · TX-1 133%
Saved engineering recordsDecisions, human actions and approval records

Saved engineering records

The decisions on this engineering desk

Built only from saved case questions, engineering work logs and review records. No invented owners, deadlines or live-plant status.

Decisions

Loading saved decisions…

Needs a human

Loading open decisions…

Approval queue

Loading review records…

Browse the engineering evidence libraryReal plants, blind studies and recorded replays ↓

Start your own project

Upload your P&ID (DEXPI XML, or a PDF that Muse reads) and paste the operating data sheet. Building the model spends Muse credit and runs only when you press Build in the workspace.

Benchmark scores: share of real engineers' conclusions the agent reached on its own, with their conclusion pages withheld, graded by a different model (muse-wonder-1.0) against an answer key taken from the withheld pages. Latest graded run per case. Draft engineering output for review by a licensed engineer.